🏗️ See the latest progress on #ElDomo construction, notably at the process plant area.
During the last two-week period:
🔹Concrete work advanced across the crushing, grinding and flotation, dewatering, and conveyor areas.
🔹Foundation excavation was completed for Conveyor No. 1
We are excited to share more pictures of our Tulkubash Gold Project in Kyrgyzstan!
These images show the site clearance for the heap-leach foundation, while the panoramic view puts the broader site into perspective. The red outline highlights the Tulkubash Zone, where the access
🏗️ The future is taking shape. ✅
Every step forward at #ElDomo reflects the commitment, planning, and hard work of those building Ecuador’s third mine. 🇪🇨
#LasNaves #Ecuador #Silvercorp #MiningThatTransforms #WeAreGrowingWithYou